Super Women’s Health gets a super upgrade with a brand new building in the heart of Suntree, Melbourne FL. This new health and wellness center is 100% designed for the comfort of its clientele. We’re hoping to move in early 2020.
Construction Timeline
January 2018 – March 2019 – Civil engineering plans, architectural plans, mechanical, plumbing, electrical plans and structural plans. County approvals.
March, 2019.- Land purchase.
April 20, 2019 – The first “big machine” appears on the lot. Exciting!
April 22, 2019 – The site construction starts. YAY!
Strange caterpillars…
April 23, 2019 – The fence is gone. Thank you Bobcat…
Saving a couple of trees.
April 24, 2019.- Silt fence is installed.
“The nicest pile of dirt I’ve ever seen” 🙂
April 30, 2019.- Fill is brought in to start raising the building pad.
May 22, 2019.- And… more fill.
Looks like Mars…
… Now it really looks like Mars… We’re on the Space Coast after all 🙂
August 2, 2019.- Preparing for launch…
Scratch that… Preparing for the stem wall footings.
August 15, 2019.- The machines are hanging out…
These are the most expenses sticks ever recorded in the history of mankind.
Niagara Fall
August 21, 2019 – Footings for the stem walls.
Wait… is there gold here???
yes there is! (Re)bars of gold 🙂
One happy camper
And one tired husband
No matter… the kids like it.
August 31, 2019 – Arriving a week later and look what we’ve got… stem walls.
September 5, 2019 – The crew is filling the pad with dirt and starts compacting.
Do not ever give her the keys! She would drive that thing…
September 10, 2019 – Beautiful site. minus the dumpster 🙂
September 12, 2019 – Rough plumbing.
September 17, 2019 – Rough plumbing complete. Slab is nearly ready to be poured.
September 18, 2019 – Vapor barrier goes in.
September 23, 2019 – Ground electrical. Some more reinforcement and ready to pour.
September 24, 2019 – The slab is being poured. YAY!!!
Looks like we can play chess now 🙂 Lots of hard work to get to that point…
October 2, 2019 – Wall blocks arrive.
Lots of blocks… A MAZ ing…
October 3, 2019 – Trusses get delivered to the job site.
October 11, 2019 – Exterior walls start going up.
Middle age castle???
Walls video time lapse:
October 16, 2019 – Exterior walls are pretty much done…
Preparing to pour concrete in the walls…
November 20, 2019 – Now is truss time.
Trusses video time lapse:
November 20, 2019 – Trusses are up. Building the roof deck is next.
November 29, 2019 – Building the overhang… and framing inside starts.
These “happy” pictures don’t show the challenges of building commercial… Maybe I should have bought my dream car instead? Less gray hair, more grin on my face… Nah, Karine and the clients deserve a world class facility…
December 9, 2019.- Doors and windows arrive.
December 13, 2019.- Plumbing rough in.
December 19, 2019.- More fill is brought in to continue the rough in of the site.
Underdrain for the parking lot.
White sand in the dry retention pond…